Skip to main content

Re: [MW:8382] PWHT and RT

Hi Mr.Sagar


For asking support clause, please refer below:


Based on below as per B31.3, P1 material not required NDE after completion of Heat treatment and this point not mentioned in code legibly; but mentioned in interpretation 19-15 (refer attachment)

 

a)    (a) Refer Para 341.3.1(a)

             "For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment"

 

b)    (b) Refer Note (11) in "NOTES FOR APPENDIX A TABLES "

"For use under this Code, radiography shall be performed after heat treatment"

             This note(11) pointing P3, P4, P5A, P5B, P9A & P9B materials only as per table A-1.


c)    (c) Refer B31.3 interpretation 19-15, Question(2)  (refer attachment)

 

"P1 or P2 materials not required NDE after final Heat treatment"



 
Rgds/Shankar



From: M.Shankar <mails_shankar@yahoo.co.in>
To: materials-welding@googlegroups.com
Sent: Wed, 17 November, 2010 7:14:24 PM
Subject: Re: [MW:8306] PWHT and RT

Hi Mr.Sagar


The election between PWHT + NDT or NDT+PWHT+NDT is a decision to take according to the criticality of service, the specific experience of welding workshop, welders skill, time schedule, costs, etc.


About PWHT:

  • PWHT does not always have a positive effect and can cause distortion and degradation of the microstructure.
  • PWHT can "open up" indications (due to heat cycle) that might not show by NDT before PWHT.
  • There is a chance for delayed cracking or post heat treatment cracking may happen in or adjacent to welds after PWHT.

Considering the above reasons NDT is preferable after PWHT to make sure the weld quality.


NDT + PWHT + NDT:

"RT before PWHT" would be an optional additional examination. Some folks do this do make sure the joint will pass RT prior to doing the PWHT. In some cases, if "RT before PWHT " is a requirement, it may be included in purchase order/specification.


If you noticed repair after PWHT, then you need repair and  re-PWHT required;to minimise/avoid this situation, preferable choice is NDT+PWHT+NDT. Repair work with re-PWHT may affect time schedule and cost impact also.


Customers always interested in NDT acceptance after PWHT.


PWHT + NDT:

However, have found that some contractors will tend to pay more attention to detail if they only shoot one RT after PWHT. Nobody wants to have to repair and perform a second PWHT.

 
Rgds/Shankar



From: Sagar QC <sagarqcwelding80@gmail.com>
To: materials-welding@googlegroups.com
Sent: Mon, 15 November, 2010 2:20:45 PM
Subject: [MW:8267] PWHT and RT

Hi,

I have a doubt regarding PWHT and RT. We are welding P1 Material Pipes which has thickness more than 19mm so we are performing PWHT for the same. But my question is regarding when to take RT? Can we accept the joints which is radiographed before PWHT and  MPI after PWHT. Or will we have to perform the RT only after PWHT of the joints? Please advice me regarding this and provide the supporting clause.

Thanks and Regards,
Sagar.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...