[MW:5161] UT scanning of Ball v/v type B8

Dear all
this is a case of UT scanning of Ball v/v type B8.

procedure says- The search unit shall be positioned for maximum response using holes at 1/4, 2/4 and 3/4.
The primary reference level shall be based on 75% of full screen height response.
but company says- Since the inspection is performed from one side only 2 DAC shall be done. The first one as suggested in the procedure and the second one starting at ¾, 6/4 and 7/4. This is to obtain a reference for full skip inspection.

can somebody give me some guidance on it?

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...