Re: [MW:14458] 2 cycle or 3 cycle PWHT

Hi!
Your PQR should be with extended Time covering total PWHT time incurred on Job(
Regards
 
Hegde


--- On Sun, 3/6/12, Sikhandar Ummer <sikhandarummer@gmail.com> wrote:

From: Sikhandar Ummer <sikhandarummer@gmail.com>
Subject: [MW:14453] 2 cycle or 3 cycle PWHT
To: "Materials & Welding" <materials-welding@googlegroups.com>
Date: Sunday, 3 June, 2012, 12:35 PM

Let me know about after PWHT we need something weld on the plate do
again PWHT then what is the requirement ?
How we will perform 2 cycle PWHT complete 2 cycle 2 time expose? or
exceed holding time?
BR,
Sikhandar Ummer

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...