Hi, You can do hydrotest seperately.because it connects with the equipment by means of bolting not by welding. Since it is an U stamp vessel, you can explain to AI to get his acceptance.
Thanks & Regards,
(Karthik)
Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066 892512282
--- On Thu, 11/18/10, THAKSEN INGOLE <t_ingole@yahoo.co.in> wrote:
From: THAKSEN INGOLE <t_ingole@yahoo.co.in> Subject: Re: [MW:8310] Possibility of hydotesting of the components of vessel To: materials-welding@googlegroups.com Date: Thursday, November 18, 2010, 2:11 PM
Dear Karthik As said below the vent nozzle is set-in with the blind flange. so PWHT is mandatory. My query is can i hydrotest only the the blind flange & 2"vent nozzle which are welded together, separately. Since the blind is bolted to the body flange, there is no weld joint in between. Does code allows this. Regards Thaksen H.O.D - DESIGN
From: Karthik <karthik6684@yahoo.com> To: materials-welding@googlegroups.com Sent: Thu, 18 November, 2010 7:07:31 AM Subject: Re: [MW:8308] Possibility of hydotesting of the components of vessel
Hi, When i look at the drawing,i think you dont need to do PWHT since it is a nozzle(2") to flange welding.I think your welding joint is fillet or groove with fillet.If it is so,and the throat thickness is not exceed 13mm,you dont need to do PWHT.
If it is of groove welds(butt joints),the nominal weld thickness exceeds 38mm need PWHT. Anyhow,without joint type i can't conclude this now. Please check your joint design and weld.If it is same as i stated then you dont need to go for PWHT.
Thanks & Regards,
(Karthik)
Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066 892512282
--- On Wed, 11/17/10, THAKSEN INGOLE <t_ingole@yahoo.co.in> wrote:
From: THAKSEN INGOLE <t_ingole@yahoo.co.in> Subject: [MW:8302] Possibility of hydotesting of the components of vessel To: "material welding" <materials-welding@googlegroups.com> Date: Wednesday, November 17, 2010, 9:23 PM
Dear All
I would like to know if it is possible to do hydrotest of individual component of a vessel. A typical case is as below.(refer the attached sketch for quick reference)
we have vessel for Aramco filters, Designed as per ASME Sec VIII Div.1 and is U stamp. The filter has 12" Standard CAP welded at one end of the 12" pipe and a top body flange 12"WNRF 300# welded at the other end of the pipe, with a 12"BLRF 300# blind flange and a 2"vent nozzle (LWNRF 300#)on the top of the blind flange. The 2"vent nozzle is welded with a "sent in" configuration to the blind flange. so this has generated the requirement of PWHT only for the blind welded along with vent nozzle , as the 12"BLRF 300# has a thickness of 50.8mm and for SA-105 material the PWHT becomes mandatory above 38mm. The vessel is stamped as PHT (partial heat treatment)
My problem. We have forgot to do PWHT for the blind flange welded to the 2"vent nozzle and the hydrotest is already performed.
Now we will do the PWHT for the blind flange welded to the 2"vent nozzle and hydrotest only these parts seperately by providing a dummy vessel arrangement to support the hydrotest of the these components . we do not want to hydrotest the complete vessel as we would like to go for blasting and painting for these vessel because of large quantity.
Is the above meeting the code requirement.
Regards Thaksen
-- To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
|
-- To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents. -- To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
|
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at
http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment