- Extended hold period is irrespective of completion of all visual inspection of system during hydrotest which is the min requirement of standard .
- Hydrotest is a proof test and whereas NDT is soundness of the weld joint. Hence extend of NDT is not be linked to Hydrotest requirements
----- Original Message -----
From: Satish Hingalkar
To: materials-welding@googlegroups.com
Sent: Fri, 1 Oct 2010 11:40:00 +0530 (IST)
Subject: Re: [MW:7300] Can we do painting prior to hydrotest?
Dear all members,
Thanks for reply on my query.
As suggested by you guys, i can say to contractor to go ahead for painting before hydrotest by holding more time upto all visiual check of joints.I have one more concern as:As per company specification, we are doing 10%MT & 10%RT that is OK or we have increase the % of MT & RT.
Please respond.
Regards,
Satish
On Thu, Sep 30, 2010 at 2:05 PM, <francis.lobo@indiatimes.com> wrote:
Dear All,
In the modern fast track projects these deviations are common , You can accept the deviation provided you extend the hold time for min 4 hrs for joints not seen or painted with chart recorder and accounting any pressure variation with tempt,
This is practiced in most of the offshore projects. However for onshore /subsea pipeline hold period is 24hrs and pressure variations vs tempt accounted.
Francis Lobo
----- Original Message -----
From: Bathula Raghuram (Mumbai - PIPING)
To: 'materials-welding@googlegroups.com'
Sent: Thu, 30 Sep 2010 15:03:40 +0530 (IST)
Subject: RE: [MW:7285] Can we do painting prior to hydrotest?
Interesting, and you have a valid point but nothing is proven, until then just go with the flow (tried and tested methods). No Inspector would be happy but bound to accept as per code. remember your company specification prohibits it and you are intended to accept, hence code reference is given, Masking of any discontinuity by thin layer of paint, may be yes perhaps may be not. If you refer the paragraphs of these codes which will give a cautionary statement at the end "painting/coating may mask the leak". Normally weld joints are left open and rest of the area is painted before hydro. In my opinion 105 bar is too high for a layer of paint to with stand, or you may allow only blasting and priming before hydro and final coating after hydro. If I remember correctly only Australian code AS1210 prohibits it.
From: Satish Hingalkar [mailto:shingalkar@gmail.com]
Sent: Thursday, September 30, 2010 12:49 PM
To: Bathula Raghuram (Mumbai - PIPING)
Subject: Re: [MW:7283] Can we do painting prior to hydrotest?
Hi,
Thanks for prompt reply
Piping system of having pipe rack near about 4 KM,service-Nitrogen,Code ASME B31.3
As u said,ASME B 31.3 allows,but my query is that whether painting will affect the joint leak detection normally found in hydrotest??
As per my knowledge,Painting has ability to penetrate and plug/ seal off small pin holes which are normally detected in hydro test. After curing, paint can withstand pressure in small pin holes that can obstruct the leaks. But during operation, paint can be decomposed and start leaking,please comment.
Regards,
Satish
On Thu, Sep 30, 2010 at 7:27 AM, Bathula Raghuram (Mumbai - PIPING) <R.Bathula@ticb.com> wrote:
You have not specified the type of component, fluid and design code. ASME code for both vessels and piping have this provision. Sec VIII div 1 allows except for lethal service (UG 99) and B31.3 allows except for sensitive leak testing (345.3.1)
From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Satish Hingalkar
Sent: Wednesday, September 29, 2010 11:55 PM
To: Materials & Welding
Subject: [MW:7276] Can we do painting prior to hydrotest?
Dear Members,
Our contractor has raised a design change request for painting prior to hydrotest.As per COMPANY specification,painting to be carried out after successfull complection of hydrotest,but contractor wants to do painting before hydrotest,can we accept this deviation? if we want to accept the deviation,what criteria to be follow??
Our design conditions are 105 barg hydrotest pressure and design temp.85 deg.c,NDT is 10% MT & 10% RT.
Waiting for reply.Pl.respond ASAP.
Regards,
Satish
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment