Please reply the below questions regarding the PWHT
1. what is the time limit to carried out the PWHT after completion of
welding as per B31.3
2. In B31.3 anywhere mention the Type of service also range of PWHT varies....
3.What will happen if PWHT will carried out after 6 Month service.
Please explain in detail with relevent clause.
Noushad
Doha
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment