Hi .
While Hydrostatic testing first you have fill water and water to settle
and air bubbles to be vented out and this leak test is a part of test
if any major leaks will be there it will come out easily depend upon
pressure.
after settlement and attaining pressure requirement, when pressure
shows constant then you can check for leaks on joint. so this process
could not complete with in 10 minute. after settlement of water you
hold it for 10 minutes . minimum it will take 30 minutes because some
Engineers will test with in 10 mins and complete. to avoid this type of
mistakes generally it is followed minimum 30 mins.
Muthu Barathi P
Senior Manager QA / QC
AFCONS
On Mon, 27 Sep 2010 14:13:17 +0530 wrote
>
See ASME B31.3, sec. 345.2.2:
345.2.2 Other Test Requirements
(a) Examination for leak. A leak test shall be maintained
for at least 10 min, and all joints and connections
shall be examined for leaks.
regards
Kristian
From:
materials-welding@googlegroups.com [mailto:materials-
welding@googlegroups.com] On
Behalf Of Shashank Vagal
Sent: 26. september 2010 13:09
To: materials-welding@googlegroups.com
Subject: Re: [MW:7205] RE: 7198] effect of longer holding time during
hydrotest
Kristen:
Please quote the clause from B31.3 about 10 min holding time. For me,
and most of us, too, this issue is unsettled. It will be a good help.
As I see it, hydrotest and strength tests have different
connotations.Please correct me if I am wrong.
Asad:
So long as you are not crossing the 75% (or as specified) SMYS
value for all components in the
loop, the holding time is a non-critical point. But
why would you want to increase it, if all your
leak test checks are completed. It does not make
sense – safety wise and economically at
least.
Shashank Vagal
--- On Sun, 26/9/10, Kristian Lund Jepsen (KUJ)
wrote:
From: Kristian Lund Jepsen (KUJ)
Subject: [MW:7200] RE: 7198] effect of longer holding time during
hydrotest
To: materials-welding@googlegroups.com
Date: Sunday, 26 September, 2010, 2:43 PM
ASME
B31.3 only require 10 minuttes hydrotest.
That
is fully enough for a strength test - and in most cases also for a
hydrostatic leak test.
But
some companies (contractors, costumers)require 30 minuttes test, some
1
hour. It will normally be stated in procedures as part of an ISO 9000
quality
system.
regards
Kristian
From:
materials-welding@googlegroups.com
[mailto:materials-welding@googlegroups.com] On Behalf Of asad azmi
Sent: 26. september 2010 07:06
To: materials-welding@googlegroups.com
Subject: [MW:7198] effect of longer holding time during hydrotest
Dear All
Goodday.
On what basis holding duration (eg.1 hour, 2houretc)
of hydrotest is decided.
What will be the effect on mechanical proerty of material
if the holding period exceeds than as required by design.
eg. suppose for a particular hydrotest holding
period is 2 hours and actual holding period exceeds to 3 hours. what
will be
the effect on mechanical proerty.
Thanks in advance for your valuable suggestions.
Best Regards
Asad Azmi
--
To post to this group, send email to materials-
welding@googlegroups.com
To unsubscribe from this group, send email to
materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-
welding.blogspot.com/
The views expressed/exchnaged in this group are members personel
views and
meant for educational purposes only, Users must take their own
decisions
w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-
welding@googlegroups.com
To unsubscribe from this group, send email to
materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-
welding.blogspot.com/
The views expressed/exchnaged in this group are members personel
views and
meant for educational purposes only, Users must take their own
decisions
w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to
materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-
welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views
and
meant for educational purposes only, Users must take their own
decisions w.r.t.
applicable code/standard/contract documents.
--
>
To post to this group, send email to materials-welding@googlegroups.com
>
To unsubscribe from this group, send email to materials-welding-
unsubscribe@googlegroups.com
>
For more options, visit this group's bolg at http://materials-
welding.blogspot.com/
>
The views expressed/exchnaged in this group are members personel views
and meant for educational purposes only, Users must take their own
decisions w.r.t. applicable code/standard/contract documents.
>
Dear Sir,
Thanking You,
Honesty is the best Policy
With Warm Regards,
P Muthu Barathi
Mobile No:09967300544
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at
http://materials-welding.blogspot.com/The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment