[MW:7276] Can we do painting prior to hydrotest?

Dear Members,
 
Our contractor has raised a design change request for painting prior to hydrotest.As per COMPANY specification,painting to be carried out after successfull complection of hydrotest,but contractor wants to do painting before hydrotest,can we accept this deviation? if  we want to accept the deviation,what criteria to be follow??
 
Our design conditions are 105 barg hydrotest pressure and design temp.85 deg.c,NDT is 10% MT & 10% RT.
 
Waiting for reply.Pl.respond ASAP.
 
Regards,
Satish

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...