Generally it depends on the WPS, being used. If WPS specify the pre-heating (at certain temperature) then it is mandatory to carry out preheat on next day morning prior to any strike.

 

As a Good engineering practice, and most of the client specification call for completing Hot pass prior to stop the welding. If you are stopping before ½ thickness deposition or hot pass, need to examine the root pass for defect by PT/MT to ensure that it is free from any cracking.

 

Regards.

 

C. K. Purohit

General Manager - QC

KNM Process Systems Sdn Bhd - Malaysia

 

HP No. : 6016-3376448


From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of rafique naik
Sent: Monday, February 09, 2009 1:16 AM
To: materials-welding@googlegroups.com
Subject: [MW:1518] Significance of HOT PASS

 

Please let me know for A 106 B 16'' dia  12.7 mm thik pipe to pipe butt joint, if after root pass joint is left as it is for overnight and next morning welder wants to continue with hot pass, can he do welding  without any pre heating..
 
Regards
 
Rafique


Need more space to upload pictures? Get 25 GB online storage with Windows Live SkyDrive! Try it!





***DISCLAIMER NOTICE ***

"This email and any files transmitted with it is confidential and is intended only for the use of the recepient(s) named above. If you are not the intended recipient, any review, retransmission, dissemination, distribution, printing, copying or use the information contained in this message or any part thereof in other manner is strictly prohibited. If you receive this email in error, please notify the sender immediately by return email and delete the email and any of its attachments. Any personal views or opinions expressed by the sender shall be understood as neither given nor endorsed by KNM or any of the companies within the Group."




--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---


No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...