Re: [MW:29232] Hot Tap welding Procedure -Welding Code

Thank you for your replies, but when we are using onplot piping wps the in service requirements are not covered in the section IX. could you please advise on this matter?

Regards
sandeep K Sreedhar

On Fri, Mar 8, 2019 at 10:57 AM Paidi <bobsuresh24@gmail.com> wrote:

"According to  P&ID the hot tap is coming under the design code B31.3." , So you must follow the WPS which is related  to on plot piping .                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      

On Fri, Mar 8, 2019 at 11:10 AM sandeep k sreedhar <sandeepkelakam@gmail.com> wrote:
Dear Experts
Greetings!
I have hot tap welding in my scope of work, According to  P&ID the hot tap is coming under the design code B31.3. 
The Hot tap welding requirement are as follows as per the client specification- ADNOC Group.

The CONTRACTOR/VENDOR shall follow procedures and qualifications specified in DGS 6300-001- WELDING AND NDE OF PIPING SYSTEM (Based on Section IX) for On-Plot Piping and DGS 6300-004- Welding and NDE of pipeline  for Off-Plot Piping- .
Welders shall be qualified in accordance with DGS 6300-001 for On-Plot Piping and DGS 6300-004 for Off-Plot Piping. 
For Off-plot pipelines, both the procedure and the welders should be qualified using a full-scale simulation of the connection, in accordance with API 1104 or equivalent COMPANY‟S specification. 

All the Hot tap sub contractor's proposing API 1104 based WPS since considering the service welding requirement.

Now I am confused which welding code has to be followed. Request for yours  kind advise on the same.


Regards

SANDEEP K SREEDHAR

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.


--
Thanks  & Best Regards,

Suresh Paidi


 

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.


--
SANDEEP K SREEDHAR
00971565359349

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...