Refer ASME sec IX
QW-405.2
If you qualify 3G position uphill, qualifies all position
Best Regards,
Chandra
Dear Expert ,--As per ASME Sec. IX QW 203 - states that a qualification in any position qualifies the procedures for all position .Now Can u all clarify one thing , I I have WPS in SMAW process and I am qualifying the PQR in 3G position , then according to above Clause it will bequalified for position .Whether its also applicable for 1G position also .Pls. clarify briefly.ThankyouS.Kharwar