Thursday, December 29, 2011

[MW:13363] Regarding Deletion of welding Process.

Dear ALLExperts,

I badly need your help for Deletion welding
Process for Using fillet welding Structural.

I have Qualified W.P.S (GTAW-root/hot+SMAW -fill/
cap)for Piping welding as per SEC-IX
& its qualified for fillet in all dia/size/
thickness & diameter as per SEC-IX.
Can I use only SMAW process for Fillet welding
In structural or Only GTAW process can be used.

Or I have to Use both GTAW+SMAW process.

Kindly Enlighten me regarding this matter or any
code clause I have to follow ( ASME-B31.3 & Shell DEP Standard.)


Thanks & Regards

Madhusudan Rout.

&

Wishing All of you & Your Families A Healthy & Prosperous New Year.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...