Hi, If your company manufacture boilers within the scope of "Section I" only and you will not do any power piping work at factory/site then you can go for S stamp accreditation only. But it is better a S stamp company apply for PP stamp also.It makes additional certificate fee only. When you are doing S stamp boiler,and some customer need to do piping work with PP stamp.At that time it will be useful to you. Thanks & Regards, (Karthik) Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066 892512282 --- On Fri, 8/19/11, kcrtechnical <kcrtechnical@gmail.com> wrote:
|
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment