Thursday, October 21, 2010

[MW:7684] MDR - ASME Sec VIII Div1

We have manufactured vessel as per ASME Sec VIII Div. 1.
This vessel is partly manufactured at shop & final assembly /
hydrotest carried at field.
My organization is having ASME U stamp certificate of authorization &
socpe covering
shop & field activities.
My question is while moving out semi finished vessel from shop to
field whether
Manufacturers Partial Data Report is required?
Field assembly & testing will be completed by same organization.

Experts / ASME Authorized Inspector's views are requested.

Thanks!

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...