Tuesday, November 11, 2008

[MW:1289] Re: FITTINGS

it is upto the designer/owner to accpet/reject and also depnds on the
time delays required to source new fittings. if these are used in
lines which are categorised as normal fluid service, you may approch
your client with a devaition request and probably with additional NDT
on the longitudinal welds of these fititngs.

On Nov 10, 10:22 pm, carlos oliveros <carlosolive...@terra.com> wrote:
>           BODY { font-family:Arial, Helvetica, sans-serif;font-size:12px; }
> Dears Friends.
>
>         I work in a project  Plant Compressor Gas under B31.3  The
> specification Project give the reference Fittings seamless and in
> Shop Fabrication the fitting are welded Elbow welded, Tee Welded. My
> question reject all fabrication or what is the solution.
>
>         Thanks
>  carlos oliveros
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...