Re: [MW:9140] Why is preheating important for welding Alloy Steel?

PREHEATING IS REQUIRED FOR HIGH ALLOY STEEL LIKE AS P91 MATERIAL , BECAUSE P91 MATERIAL IS CORE GRAIN MATERIAL, WHICH IS MOST HARD MATERIAL, AND THE GRAIN SIZE IS VERY HARD, SO BROKEN OR MELT THIS GRAIN SIZE WE PREHEAT THE MATERIAL AT 250 YO 350C, DEPENDING UPON THICKNESS, OTHERWISE WE DO NOT APPLY PREHEAT ON MATERIALON HIGH ALLOY WELDING CRACK DEFENTLY FOUND.

On Fri, Jan 7, 2011 at 1:20 PM, Suresh Babu <suresh75.babu@gmail.com> wrote:
Dear Team..i would like to get a correct answer for the following
question.

Why is preheating important for welding Alloy Steel?

Thanks in advance
SURESH.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...