Wednesday, October 27, 2010

Re: [MW:7841] PWHT Requirement

Hi,
Please find below my simple comments as marked in red.
 
1. what is the time limit to carried out the PWHT after completion of
welding as per B31.3
 
There is no time limit for PWHT except P.No.62 as mentioned in Table 331.1.1, note.10.
But Definition of PWHT is heat treatment shall be done immedietely after final welding finished.
Also pls.refer 331.2.4 Delayed Heat tretament and 331.2.5 partial heattreatment.
 
2. In B31.3 anywhere mention the Type of service also range of PWHT varies....
 
Code specifies that,heat treatment requirements shall be decided by the designer according to the service conditions.
Please refer 331.2 - Specific requirements
Category M Fluid Service - follow B31.3 - Chapter-VIII - M331
High Pressure Piping - follow B31.3-Chapter-IX - K331
 
3.What will happen if PWHT will carried out after 6 Month service.
Please explain in detail with relevent clause.

pls.refer 331.2.4 Delayed Heat tretament and 331.2.5 partial heattreatment.
Delay in PWHT may result of cold cracking.
 
Thanks & Regards,
 
(Karthik)

Karthikeyan.S
QA/QC Manager
Getabec Energy Co.,Ltd.
379,Moo6,Soi8,Nikhomphatana,
Rayong-21180,
Thailand.
Phone: 0066 38 897035-8 (Off)
Fax: 0066 38 897034
Hand Phone: 0066 892512282


--- On Tue, 10/26/10, Noushad cp <ncp.clt@gmail.com> wrote:

From: Noushad cp <ncp.clt@gmail.com>
Subject: [MW:7833] PWHT Requirement
To: "materials-welding" <materials-welding@googlegroups.com>
Date: Tuesday, October 26, 2010, 6:27 PM

Dear All,

Please reply the below questions regarding the PWHT

1. what is the time limit to carried out the PWHT after completion of
welding as per B31.3

2. In B31.3 anywhere mention the Type of service also range of PWHT varies....

3.What will happen if PWHT will carried out after 6 Month service.

Please explain in detail with relevent clause.

Noushad
Doha

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.