Dear Experts,
I had a query regarding Nozzle and its RF Pad oppenings and
attachments near the welded joints and over the welded joints as per
ASME Sec 8 Div 1. I also attached a detailed sketch drawing for your
kind reference.
1) Reinforced opening ( RN ) near the Weld Joints :
a) What is the minimum distance between vertical /
horizontal welded joints and Nozzle RF Pad fillet weld joints [A],
[B], [C].
b) What is the minimum distance between RF Pad joint and
Non reinforced Nozzle fillet joints [ E ].
2) Reinforced opening ( RN ) Over the Weld Joints :
a) What is the RT requirements ?
3) Non Renforced opening ( SN ) near the Weld Joints :
a) What is the minimum distance between Vertical /
Horizontal weled joint and Non reinforced Nozzle fillet joints [ E ].
4) Non Renforced opening ( SN ) Over the Weld Joints :
a) What is the RT requirements ?
So please kindly go thru my query and help me in this regard .

Thank Regards,
BALAMURUGAN.M,
QA/QC ENGG,
L&T ECC,
ODISHA,
INDIA.
PH - +918763569606

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...