better if u have 3 cycled qualified PQR.this will cover your post PWHT
repair if any arise after NDE(RT).
On Jun 4, 1:19 pm, asad azmi <azmiasada...@gmail.com> wrote:
> Dear All,
>
> Greetings.
>
> A Vessel of CS MATERIAL, 10 thk, is having Simulation ( 3 Cycles PWHT)
> requirement. PWHT soaking time for the vessel is 2 hours.PWHT is Service
> Requirement.
>
> construction code - ASME sec VIII Div 1.
>
> Whether PQR Should have 3 Cycles PWHT or Single cycle PWHT only.
>
> Thanks and Regards
>
> Asad Azmi
--