Re: [MW:10506] WPS

 
Dear Manoj,
 
Please find the Attachment related to your Query No.1.
 
Thanks & Regards
Vino- Doha

____________________________________________________________________
On Sun, Mar 27, 2011 at 1:28 PM, manoj john <manojacgnr@gmail.com> wrote:
Dear members,

I have one query regarding WPS.

1) One of my client made a comment on a WPS which i had submitted to
them for approvel that  Procedures are from 2001.  My question is Is
there any time limit for WPS?  In my knowledge answer is No, a
qulified procedure can be used any time without changing the essential
variable.

2) I have one  qualified wps with base metal S 355 JR to S 275 JR.
Can I use this WPS to weld  S 355 JR to S 355 JR and S 275 JR to S 275
JR?

Please clear my doubts, if possible with code reference.

Thanks & Regards.

Manoj

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34832] Inquiry about Single Bevel with Back Grinding

Dear Uday, As per your question that one is called with backing only,Simple both side you are welding it is backing with strip or without st...