Dear members,

I have one query regarding WPS.

1) One of my client made a comment on a WPS which i had submitted to
them for approvel that Procedures are from 2001. My question is Is
there any time limit for WPS? In my knowledge answer is No, a
qulified procedure can be used any time without changing the essential
variable.

2) I have one qualified wps with base metal S 355 JR to S 275 JR.
Can I use this WPS to weld S 355 JR to S 355 JR and S 275 JR to S 275
JR?

Please clear my doubts, if possible with code reference.

Thanks & Regards.

Manoj

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...