Thursday, March 31, 2011

[MW:10549] Pqr

Dear all
 
We have a previous project qualified welding procedure, but hardness test carried out in old method in that pqr, present project spec is saying that requirement of test as per NACE MR0715 ISO 15156. i have some doubts about it
 
we can weld a coupon as per wps and do the hardness test as per nace requirment or need to qualify newly with all tests
pls send the reply with code reference
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone