Hi, The welder can be accept for 3F and 4F shall be retested.Code doesn't restrict to reject both.But in some Project specifications/Customer rejects both if you do qualification 2 or more positions quaified at the same time.
Thanks & Regards,
(Karthik)
Karthikeyan.S QA/QC Manager Getabec Energy Co.,Ltd. 379,Moo6,Soi8,Nikhomphatana, Rayong-21180, Thailand. Phone: 0066 38 897035-8 (Off) Fax: 0066 38 897034 Hand Phone: 0066 892512282
--- On Wed, 3/16/11, raja n <rajandt1@yahoo.com> wrote:
From: raja n <rajandt1@yahoo.com> Subject: [MW:10390] WQT To: materials-welding@googlegroups.com Date: Wednesday, March 16, 2011, 6:20 PM
Dear experts, Good day for all. While qualifying performance qualification for the welder with 3F and 4F fillet welds, I had noticed lot of undercuts and poor weld profile so I have rejected 4F piece. But 3F weld somewhat ok and its accepted. I have to qualify this welder as per section IX. As far as performance qualification is concerned if the one piece is failed the entire qualification test is failed.But our contractor insist me to accept 3F. Should I reject both pieces or reject only one which is failed. Kindly someone correct me if i am wrong and if possibel refer the para in section IX or from QW-300 of section IX. Thanks and regards Raja K | | -- To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
|
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at
http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment