i am workig in cross country pipeline,as per WPS the preheating temp. for carbon steel (Gr. X56, X65) is 100 degree, and in plant for carbon steel the preheating temp. is 10 degree that means there is no requirement of preheating, somebody has told me in pipeline the preheating is done only to remove the moisture on the surface of metal otherwise there is no any requirement of preheating, is it proper reason, pls share your experience.

--
Thanks and Regards
Hemant F Wadibhasme
Sr. QA/QC Engineer.
Larsen and Toubro
ECC Division.
Contact No. 09727083772

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...