I do not think that a factory pipe, which must have the manufacturer's name, heat, specification, diameter and schedule, have to bring a Partial Data Report, I have never seen such a thing, but ask your assigned Authorized Inspector .
El lun., 16 mar. 2020 a las 3:39, chiluka venkatramulu (<ramuluchiluka@gmail.com>) escribió:
Dear All,--Pl clarify the below requirement.If welded pipe required in U-stamp job, is the pipe manufacturer should have U-stamp certification?. Such material must be furnished with a Code PartialData Report for Welded Construction (Form U-2 or U-2A)?Thanks & Regards,Venkatramulu CH
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAF98%2BdHm2ve87wD_F_KN6usSXo%2Bfe4OLA-Ozqig6Hdo%3DNYBbMw%40mail.gmail.com.
Ing. José Juan Jiménez Alejandro
Independent Consultant in Parts
and Pressure Equipment
SSI-TPI
Móvil +52 1 812 352 4606
Skype: jjjimeneza
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAO5Zur%2BkirJQqxvBETEvy-9w2czdNBbTeoSZrtnksdXxB_%3DiCQ%40mail.gmail.com.