Friday, March 6, 2020

[MW:30607] As per API 650 Bottom LS joint with Backing strip RT required or not

Dear experts,

Please suggest  RT required or not As Per API 650 ,  For  Bottom LS joint with Backing strip .

If required how much Percentage?

Regards,
Dhakshnamoorthy.J

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAHHcqJeiVh56vPQiww%2BtqhKRWi_qDByHS4O%2BpWyg6GoQ5HkhWw%40mail.gmail.com.

No comments:

Re: [MW:35507] WPS for Furnace PWHT

As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...