Monday, March 16, 2020

[MW:30631] Welded pipe for U-Stamp Job

Dear All,
Pl clarify the below requirement.
If welded pipe required in U-stamp job, is the pipe manufacturer should have U-stamp certification?. Such material must be furnished with a Code Partial
Data Report for Welded Construction (Form U-2 or U-2A)?

Thanks & Regards,
Venkatramulu CH

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAF98%2BdHm2ve87wD_F_KN6usSXo%2Bfe4OLA-Ozqig6Hdo%3DNYBbMw%40mail.gmail.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...