Dear All,
 The Query is, how to define S & PP stamp. 
I hope S refer to code ASME Sec.I and PP refers to code ASME Sec B31.1.
what is external piping and proper?.
For example, if any client says to do external piping and stamp as S means how to justify whether it is correct or not. please clarify.

if S stamp means how to start it?

if PP means how to start?

--
Regards,
J.C.Andrews
QA/QC Engineer
Doha-Qatar.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...