Friday, November 30, 2012

[MW:16096] Regarding clarification in S Stamp and PP Stamp.

Dear All,
 The Query is, how to define S & PP stamp. 
I hope S refer to code ASME Sec.I and PP refers to code ASME Sec B31.1.
what is external piping and proper?.
For example, if any client says to do external piping and stamp as S means how to justify whether it is correct or not. please clarify.

if S stamp means how to start it?

if PP means how to start?

--
Regards,
J.C.Andrews
QA/QC Engineer
Doha-Qatar.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...