Reference para 7.4 from SA 420 WPL6 states "When the fittings are to be post-weld heat treated after being welded by the purchaser and when so specified in the order, the test specimens shall be subjected to the same post-weld heat treatment. The purchaser shall use the post weld heat treatment shown in Table 2, unless otherwise specified in the order."
Question 1) Since ASME Sec VIII Div 1 UCS 85(e) does not call for simulation heat treatment for P1 material for the standard component, however as per the clause 7.4 of SA 420 WPL 6 Is it necessary (In order to meet the ASME requirement) for the vessel manufacturer to inform the fitting supplier that the vessel is going to be used in a vessel and that the vessel is going to be post weld heat treated and the fitting need simulation heat treatment?
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment