Hai,
For On plot piping ref- B-31.3, and for off plot ref - API-1104,
on plot is comming under process area (process piping )and off plot in Hydrocarbon area ( flow lines ).
From: pradip kumar sil <pradipsil@gmail.com>
To: materials-welding@googlegroups.com
Sent: Thu, April 21, 2011 3:12:46 PM
Subject: [MW:10783] ON PLOT PIPING & OFF PLOT PIPING
Dear all,
Thanks for previous reply. Now i have one more query , What is the limitation of " ON PLOT PIPING & OFF PLOT PIPING"
Regards
Pradip
--To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.