Thursday, December 2, 2010

RE: [MW:8472] OPENINGS IN OR ADJACENT TO WELDS

Yes, follow the requirements of UW14.

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Santosh Gaikwad
Sent: Thursday, December 02, 2010 2:48 AM
To: materials-welding@googlegroups.com
Subject: [MW:8470] Joint Efficiency

 

Dear all,
my company is manufacturing ASME U Stamp vessel,as per the drawing one of the nozzle location is very closed to the dish head circumferential seam,even Dish head welding & nozzle welding are touching together .

is it acceptable as per ASME Sec VIII div I .

please do reply. 

--
Thanks & Regards.

Santosh Gaikwad


No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...