Wednesday, December 13, 2017

Re: [MW:27179] Welder Qualification for E & I work

Dear,

First you should have a WPS before proceeding for WQT. Analyze and ask for position from the respective engineer. Accordingly qualify the welders. Test and plate requirements were given in SEC IX. Kindly refer.  


Thanks with warm regards,

Pramodh Ramanunny
+919633251371

If We Work With Determination And Perfection, Success Will Follow



On Tuesday, December 12, 2017, 7:26:59 PM GMT+3, pavan kumar reddy Juturu <pavan2k20@gmail.com> wrote:


Dear Experts, 

Kindly give your suggestion that in which position WQT should carry out Electrical and instrumentation cable tray and supports welding work, and what should the size of test piece.

Thanking you,

Pavan.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...