Hello Experts,
-- Query - We have one of the Vendor PQR for P4 material and noticed that the PWHT has been carried for 2 hours (Thickness = 23.5mm). I believe that the PWHT time should not be more than 1 hour for the said thickness.
Question 1 # Whether for any new job using the same PQR, PWHT time should be the same 2 hours or it can be reduced to 1 hour as per the latest standard? We have currently a modification job in the same steam line and the thickness is 10.0 mm.
Question 2 # What could be the reason for this 2 hours, PWHT time period?
ASME - B31.3, 2006 Edition
Line Service - High Pressure Steam
Let me know if any further detail or clarification is required.
Thanks.
Regards
Vino
Qatar
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAM7oz7C%3DuBP1%2Bx_647zQ_UrtNSWuz8sb73B_hNTUuH_qROEHEg%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment