[MW:26476] Golden weld requierements

Dear experts ;

We have a power piping project ( B31.1 ) and our subcontractor is only performing RT or UT for golden weld , I know that it should be full NDE but I can't find this requirement in the code .
Can somebody give me the exact requierements for golden weld ?

Many thanx

No comments:

Re: [MW:35507] WPS for Furnace PWHT

As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...