BSR is Not Necessary, if there is client requirement you have to take BSR otherwise you can pass the joint by taking ASR

On Monday, November 15, 2010 at 10:20:45 AM UTC+4, Sagar QC wrote:
Hi,

I have a doubt regarding PWHT and RT. We are welding P1 Material Pipes which has thickness more than 19mm so we are performing PWHT for the same. But my question is regarding when to take RT? Can we accept the joints which is radiographed before PWHT and  MPI after PWHT. Or will we have to perform the RT only after PWHT of the joints? Please advice me regarding this and provide the supporting clause.

Thanks and Regards,
Sagar.

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/8511fb39-08df-4240-b373-399fd200da40%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...