First of all ....before any Qulification WPS and PQR ......you have develop a Preliminary ...or proposed WPS ....which will be base on material ...welding process consumable....and the scope of your application ...
According with Proposed WPS ...you will perform ...qualification .welding test.... base on you will record all data per runs ...speed ...heat input. .interpass temp....
After the welding test piece was done...after RT .is gone for mechanical test ....and base on will be issued PQR......according with your satisfactory results ...will be issued final WPS that will be applied to future production welding (on wps will be specified the PQR numer supported)
regards
--
Daniel Iordache
Bureau Veritas - Angola
Mechanical& Welding Surveyor
Mobile Ao: +244921544583
Mobile Ro: +40721731728
E-Mail: daniel.iordache@gmail.com
daniel_iordache@yahoo.com
-- On Wed, Dec 30, 2009 at 1:31 PM, mahen dran <cbemahendar@yahoo.com> wrote:
--Dear GroupGood day,--------------------------------------------------------------------------------------------------------------------------------Still I have confusion on WPS and PQR terms.1. WPS to be created first , with respect to selection of process, electrode and current etc.2. PQR is developed after WPS ,by entering the the actual variation relevant to the WPS.|Corresponding reference numbers are to be entered in each other.This is the information from ASME IX codes.--------------------------------------------------------------------------------------------------------------------------But there is a controvercial statement from some of our colleques, PQR to be developed first and Supporiting PQR reference number is to be entered in the WPS.Please clarify this confusion .mahendraKSA
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
Daniel Iordache
Bureau Veritas - Angola
Mechanical& Welding Surveyor
Mobile Ao: +244921544583
Mobile Ro: +40721731728
E-Mail: daniel.iordache@gmail.com
daniel_iordache@yahoo.com
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment