[MW:2025] EN 287-1 welder qualification

Hello,

i have the following situation.......

welder qualification for piping 4" sch 80 BW - h-l045........is that
cover also fillet weld(exemple: fillet weld between annular plate and
first shell of tank) ...or is necessary to perform on pipe over 6"....

thanks

BV Surveyor

Daniel Iordaache

--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:34874] ASME IX, groove weld during WQT limits for Fillet Weld production

Hi David,  There are two points in WQT. 1. Thickness of Base Metal -T 2. Thickness of Weld Metal -t When you use a combination of two proces...