Re: [MW:31487] Prequalified WPS Essential variables for AWS D1.1 Table3.7 with Table 4.1&4.2

Table 3.7 is for pwps
Table 4.1 & 4.2 - WPS requirements.

Both scope the std have different table of essential variables.

So. You must prepare one pwps for fillet.
2015 edition have seperate joint configuration for fillet joints in PWPS.



என்றும் அன்புடன்,
Thanks & Regards,
RAJAVARMAN
+971561895584

On Mon, Sep 21, 2020, 7:37 AM QC Engineer <binoypl3@gmail.com> wrote:
Dear Experts,

As per the PWPS essential variables given in Table 3.7 -23 of AWS D1.1,
and comparing it with Table 4.1&4.2,is it permitted to use the Prequalified WPS made for Butt joint welding for FIllet welding also.?


Table 4.1 &4.2 is applicable to Prequalified WPS or not?

Regards



--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/70d11f92-f4e5-4719-8604-9131eb30b698o%40googlegroups.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CA%2BHpzU5gcU81F7Y-8wN7txBPXoOO0uLZy4Dy2tWX8qgbke%2BdmA%40mail.gmail.com.

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...