Dear sir,
I have two WPS and PQR separately.
1) SMAW up to 32mm
2) GMAW up to 32mm
But while using combination if these two process, is it necessary for me prepare separate PQR or by combining these two available PQR we can make third WPS.
Regards
Prasad
--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/37b8af07-fc52-4070-adb8-6e5c925c8712%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
Subscribe to:
Post Comments (Atom)
Re: [MW:35501] TEST COUPON ASME SEC IX
Yes, You can machine the Plate. Prepare the Welding Running Sheet and mention 14 mm Plate machined to 8 mm Plate. then the groove weld qua...
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-