Please refer QW-201 Manufacturer's or Contractor's Responsibility (ASME IX - 2011) .It solves your query.
-- Thanks,
Sundar
On Thursday, November 19, 2015 at 6:50:01 AM UTC+3, dominic v.k.dominic wrote:
On Thursday, November 19, 2015 at 6:50:01 AM UTC+3, dominic v.k.dominic wrote:
Dear Expertise,The contractor submitted other project PQR and approved by some other third party company and client.My Question: Can used other client approved PQR for this new project and new Client?In the code (API-1104 and ASME Section -IX) anywhere specified in this matter for Employer can be used other project PQR-If matching According the codes and new client requirements.If yes, please provide code reference.Thanks in Advance.Best Regards,Dominic.
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/9129bd1f-1407-46f3-9799-5f1c37e5fc94%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment