Dear Ahmad,
Below are my replies in rough figure
Piping prefbarication: 60 inch/Welder/day
Piping prefbarication: 60 inch/Welder/day
Piping erection: 20 inch/welder/day
Pipeline: 40 inch/welder/day
Spherical tanks 40mm thick: 35 cm/welder/day in production and 20 cm/Day in repair
The above values Could be affected in plus/minus depending on the welder, the welding procedure (TIG/SMAW orSMAW..).....
BR
Sent from my ThinkPad S230u
--Dear experts
Dose any one have a formula(s) or table to calculate the standard productivity for welders regarding the pipe diameter and schedulefor1-pipe fabrication and erection
2-pipe lines
3- spherical and cylindrical tanks
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment