Re: Re: [MW:9847] WELDING PROBLEM

Eldho,

Further to trailing mail, welding electrodes E6010 and E7010 are not suitable for welding of API 5L X65.

Check the strength.

Regards.

John



The Pipe is = API 5L -Gr.X65Electrodes are E6010 (Root) and E7010(Filler+ Capping)Code : API 1104.

On Sat, 12 Feb 2011 19:09:34 +0530 wrote
>Eldho,
>
Good morning,
>
If there is specifiction for this project, it will dominate requirements of API 1104. My advise for you is as below.
>

>
Check the time between weld passes listed on WPS. Time beween passes is essential variable as per API 1104, clause 5.4.2.8.
>
Clause says "An increase in maximum time bteween completion of root bead and start of second bead (hot pass) constitute an essential veriable"
>

>
What to do after hot pass or second bead? Code is silent. It does not say anythig.
>
It is upto manufacturer to decide. In other words, time between weld passes after hot pass (second bead after root pass) is non-essential variable.
>

>
There is no need to cut the joints. You can proceed with welding provided,
>
1. Proper buffing is carried out to remove rust
>
2. Maintain interpass temperature as per project approved procedure.
>

>
I told you earlier as well, all answers are in code book. Do you remember? Just read it with interest.
>

>
Have a nice day.
>

>
John Rodrigues
>

>

>

>

>

>
On Sat, 12 Feb 2011 18:50:34 +0530 wrote
>
>Dear All,
>
Presently I am working in a crosspipelineproject, an unexpected problem hasoccurredduring the production,due towhichthe welding had to be stopped,but there is 19 joints which has completed only the (root +hot-pass),still there is (Filler 1 + Filler 2 + Capping) balance and the joints has been left open for more than 48hrs.
>
My doubt is, if I want to resume the welding now ,whether I have to cut out all the 19 joints andre-weld ?orShould I reheat and resume with the welding.?
>
If the joints has to be cut out where is it mentioned so (any applicable code)
>
The Pipe is = API 5L -Gr.X65Electrodes are E6010 (Root) and E7010(Filler+ Capping)Code : API 1104.
>

>
Kindly please suggest your expert advices on this issue.
>
Thanking You,
>
Eldho Isaac.
>

>

>

>

>
--
>
>
>
To post to this group, send email to materials-welding@googlegroups.com
>
>
>
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
>
>
>
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
>
>
>
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
>
>
>



>
John Rodrigues




John Rodrigues

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...