Monday, December 20, 2010

RE: [MW:8824] WQT

Pl. specify your code of constriction and additional contractual requirements, ASME IX doesn’t require both (RT as well as Mechanical tests) for WQT, unless it is specified in your contract or some other codes are applicable like IBR or high pressure piping (chapter IX in B31.3). In this case you have wait till completion of all the tests are done.

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Rishikesh Singh
Sent: Monday, December 20, 2010 9:18 AM
To: materials-welding@googlegroups.com; kgpandithan@gmail.com
Subject: [MW:8823] WQT

 

Dear Sirs,

 

I want to know that in welder qualification test if the NDT is cleared and the Destructive testing is awaited then can we start our production weld with these welders and what happen in case  the Destructive examination is failed please reply Sir i m suffering with this problem please.


Regards,
 
Rishikesh Singh
Project Engineer(Bharuch)
A.I.P.L.
8128769028


No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...