Sunday, November 13, 2022

[MW:33702] Clarification regarding pwht

Dear experts.
                         ASTM A335 P91,Joint welding completed,Rt done ,third party NDT RTFI result RT pass,as per ITP PWHT should be done with in 24 hrs of welding completion,so PWHT done,but Aramco Oid dis agreed with third party Result, result given as repair, Repair done,can we perform PWHT ?if  we do stress release again,is there any specific standard?

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAO8WSnEtfDTjU8Vn%3DdkwksojzKzODCdgSJ3NiN3VFvPZUwQvxw%40mail.gmail.com.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...