7018 or 7010 Should be defined by WPS and validated by PQR.
On Tue, Jun 13, 2017 at 12:44 PM, Shankar S <sshankar.irs@gmail.com> wrote:
Dear experts,--At one particular LPG bottling plant contractor proposed WQT approval root run as E6010 and fill as E7010. I have doubt that E7018 is suppose use for fill up only.Project: Pipeline. Pipe specification PSL2( API)- Oil & Gas. Ref. standards: API 1104, ASME B 31.4/8.Please suggest accordingly.Thanks in Advance.regards,ShankarHyderabad India.
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com .
Visit this group at https://groups.google.com/group/materials-welding .
For more options, visit https://groups.google.com/d/optout .
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment