[MW:16414] Re: Socket weld gap requirement

here is an interesting article relevant to the subject

http://www.hera.org.nz/Story?Action=View&Story_id=1578


On Saturday, September 22, 2012 8:19:28 PM UTC+5:30, Nareshkumar Subramanian wrote:
Dear experts,

As per ASME 3.1.& 31.3 socket weld gap requirement is 1/16" before welding. Whether it is required for after welding, if its require kindly provide the code details.In our project we're done RT for socket welds. But after welding did not find the 1/16" gap, its less than 0.5mm. Our client decision is to cut and reweld the all joints.
 
 
Thanks & Regards,
Naresh

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...