Hi.
No need to established new WPS for p11 material with purging gas for further details see QW 408.9
Regards
Neilashkumar
Welding/Engineer
GB ENGINEERING ENT P LTD
--- On Sat, 23/7/11, pradip kumar sil <pradipsil@gmail.com> wrote:
From: pradip kumar sil <pradipsil@gmail.com> Subject: [MW:11877] P-11 with purging To: materials-welding@googlegroups.com Date: Saturday, 23 July, 2011, 3:29 PM
Hi, I have one ESTABLISHED WPS for P-11 which is not purged by argon but as per our client specification purging is required for P-11. Can anybody tell me can i use ESTABLISHED WPS for with purged condition. For that one, what is the criteria & where it is written in code. Regards Pradip -- To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
|
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at
http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment