Skip to main content

[MW:6325] FW: 6309] Asme Stamps according section VIII division 2


 

Dear  Mr Arunachalam & Mr Guttemberg,

 

I would concur with the suggestions provided by Mr Arunachalam in general. However  in my opinion few additional requirements may have to be incorporated.

 

The scenario is similar- where X organization performs shop fabrication and Y-organization performs field assembly, welding and final inspection. In this present circumstances  the vessel was fabricated and shipped in one piece by X and it had to be weld repaired and inspected and tested by Y.

 

Manufacturers' Data report, Form A-1 was completed by the original fabricator (X) and was sent to the  owner of this equipment along with shipment. Since the second organization(Y) would be performing the repair, Form A-2 ,Manufacturer's Partial Data Report should be filled up by them  and to be endorsed by the local Authorized Inspector.

 

The organization performing repair should have both ASME U-2  & R stamp.

 

Below  is the extract from DIV-2 (Clause 1.2.6)   on performing field welding and assembly work.

 

Thanks.

 

Pradip Goswami,P.Eng

Senior Engineer/Specialist(Welding-Metallurgy)

Component Integrity Dept.

Engineering & Training Services Division

ONTARIO POWER GENERATION Inc.

 

1.2.6 Field Assembly of Vessels

Field assembly of vessels constructed to this Division may be performed as follows.

·         The Manufacturer of the vessel completes the vessel in the field, completes the Form A-1 Manufacturer's Data Report, and stamps the vessel.

·         The Manufacturer of parts of a vessel to be completed in the field by some other party stamps these parts in accordance with Code rules and supplies the Form A-2 Manufacturer's Partial Data Report to the other party. The other party, who must hold a valid U2 Certificate of Authorization, makes the final assembly, performs the required NDE, performs the final pressure test, completes the Form A-1 Manufacturer's Data Report, and stamps the vessel.

·         The field portion of the work is completed by a holder of a valid U2 Certificate of Authorization other than the vessel Manufacturer. The stamp holder performing the field work is required to supply a Form A-2Manufacturer's Partial Data Report covering the portion of the work completed by his organization(including data on the pressure test if conducted by the stamp holder performing the field work) to the Manufacturer responsible for the Code vessel. The vessel Manufacturer applies his U2 Stamp in the presence of a representative from his Inspection Agency and completes the Form A-1 Manufacturer's Data Report with his Inspector

 

 


From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of Arunachalam A
Sent: Wednesday, August 04, 2010 12:05 PM
To: materials-welding@googlegroups.com
Subject: Re: [MW:6309] Asme Stamps according section VIII division 2

Any repairs to U2 stamped vessel shall be as follows:

1. Any repairs shall be done by an R-Stamp holder, who should also have U2 stamp for new construction.

2. R-Stamp holder shall prepare a repair plan which shall be in conformance with UDS, Manufacturer's design report and MDR.

3. Repair plan shall be sent to an Registered Professional Engineer for his certification.

4. Once his certification is completed, the repair plan along with Drawing/UDS/Manufacturer's design report/MDR shall be submitted to ASME Authorized Inspector, with whom the R-Stamp holder has an Inspection agreement.

5. AI inspects the vessel and agrees with repair plan.

6. R-Stamp holder Carries out repair.

7. Carries out NDE and /Or hydrostatic set as per Repair plan.

8. After AI accepts the repair completion inspection, he authorizes R-Stamping.

9. R-Stamp holder prepares, and gets it certified by AI.

 

arun

 

On Wed, Aug 4, 2010 at 3:56 AM, guttemberg.souza <guttemberg.souza@uol.com.br> wrote:

Dear All,

Who can help me about a case regarding a pressure vessel stamped as "U2" which was manufactured, approved and shipped to the company i work for. But during the receiving inspection, in order to fit it to its final position, and according to internal inspection, some defects have been revealed on the visual weld inspection on the root of one of its nozzle like undercutting, lack of fusion and concavity. We asked for the x-ray film to the manufacturer and they have sent to us but the result was approved. Then we have decided to perform another x-ray  on that joint to confirm the manufacturer x-ray, using the same x-ray technique and the result revealed porosities out of ASME VIII div 2 requirements. So, in this case, if we decide to repair this joint, would we need to classify the vessel again ?

Best regards,


Guttemberg Souza

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.




--
அருணாசலம்
கலைவாணி
சுதர்ஷனா
வருண்

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.


THIS MESSAGE IS ONLY INTENDED FOR THE USE OF THE INTENDED RECIPIENT(S) AND MAY CONTAIN INFORMATION THAT IS PRIVILEGED, PROPRIETARY AND/OR CONFIDENTIAL. If you are not the intended recipient, you are hereby notified that any review, retransmission, dissemination, distribution, copying, conversion to hard copy or other use of this communication is strictly prohibited. If you are not the intended recipient and have received this message in error, please notify me by return e-mail and delete this message from your system. Ontario Power Generation Inc.

Comments

Popular posts from this blog

Materails FAQs

Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? (asked by: boris.vielhaber@vait.com) A: DIN Nr. = 2393 T.2, 2394 T.2, EN 10025 W. Nr. DIN 17007 = 1.0038 Design DIN 17006 = RSt 37-2, S235JRG2 (Fe 360 B) Q: What is St DIN 2391 BK material? (asked by: dmcandrews@automaticstamp.com) A: Precision steel tubes, cold-finished/hard. Q: What is C.D.W. Boiler Tube? (asked by: montydude123@yahoo.com) A: Cold Drawn Welded Boiler Tube. Q: WHAT IS W.Nr. 1.4301? PLS TELL US IN EASY LANGUAGUE (asked...

Heat tint (temper) colours on stainless steel surfaces heated in air // Heat tint

Introduction The colour formed when stainless steel is heated, either in a furnace application or in the heat affected zone of welds, is dependent on several factors that are related to the oxidation resistance of the steel. The heat tint or temper colour formed is caused by the progressive thickening of the surface oxide layer and so, as temperature is increased, the colours change.   Oxidation resistance of stainless steels However, there are several factors that affect the degree of colour change and so there is no a single table of colour and temperature that represents all cases. The colours formed can only be used as an indication of the temperature to which the steel has been heated. Factors affecting the heat tint colours formed Steel composition The chromium content is the most important single factor affecting oxidation resistance. The higher the chromium, the more heat resistant the steel and so the development of the heat tint colou...

Re: [MW:10788] ON PLOT PIPING & OFF PLOT PIPING

Piping systems involved for the flow lines and gathering lines from the well head isolation valve to the production facility or processing plant isolation valve are determined as OFF PLOT. ON PLOT defines piping system in the processing plant and production platform. ANSI/ASME B31.4 applies for off plot piping system. B31.4 allows the use of either API 1104 or ASME section IX (as appropriate). However, occasionally, a very small system such as piping within 500 feet of a processing plant (some client also said 400 feet) may be declared B31.3 rather than B31.4. When B31.3 is invoked, only ASME Section IX is used. before you decide which code to use for welding procedure and/or welder qualification for pipe welding, you have to know the design and construction code applicable to the system. Please read far enough into scope and diagram illustrating the application of either B31.3 and B31.4 hope this helps rgds 2011/4/21 pradip kumar sil < pradipsil@gmail.com > Dear all, ...