Please advise me if you have WPS for P91 material without PWHT….
PWHT is time consuming..
Thanks and Regards,
asfaruk
As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...