Hi Experts,
I would like to know about PWHT Requirement as per ASME B31.3 Edition 2014.
Actually for P1 Material as per Table 331.1.1 given Soaking Temperature & time for all thicknesses.
Also as per Table 331.1.3 given some exemption for PWHT of P1 material subject to two limitations ie. One for greater than 25mm thickness a preheat of 95 Deg C to be applied whereas other one is for greater than 5mm Thk multiple layer of Welding carried out.
So my question is, If thickness is of 50mm and if we are covering both the condition of preheat and multiple layer Welding then PWHT is applicable or not?

Kindly need your advise...

Thanks & Regards
Krishna Mudhale
Mob.:+91-9860459776

--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAG8LsMacsw5LMv27PSeN_DzEHztwhkpdHpn2qxOREF3SX_0MXw%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone